City Council members vote Tuesday night on whether to stop new data center development in Denton for 90 days while staff write more detailed technical rules for the industry.
The moratorium is up for its second reading at the Dec. 1 regular meeting, which starts at 6:30 p.m. at City Hall, 215 E. McKinney St. State law requires a supermajority for approval: at least three-fourths of the full council, according to the staff report.
What the pause would cover
The ordinance would halt commercial data center development inside the city limits, in the city's water and sewer certificated service areas and in the area Denton Municipal Electric is certified to serve. Projects with applications already filed are protected by state vested-rights law and cannot be stopped.
A developer could also ask for a waiver by pointing to an existing development agreement or by offering to pay for the missing public facilities, the staff report says.
The pause would end after 90 days or once the council adopts the new rules, whichever comes first. Staff say state law allows one 90-day extension, for a maximum of 180 days, and bars a new moratorium on the same area for two years.
The city's stated reasons
Staff built the case on three findings allowed under the state's moratorium statute. On water, the city can produce up to 48 million gallons a day, and peak-day demand reaches 42.2 million.
On wastewater, the Pecan Creek Water Reclamation Plant is rated for 21 million gallons a day but handles 25.7 million on peak days, a shortfall of 4.7 million that the ordinance's exhibit describes as operating in a deficit.
On electricity, the report says DME has about 75 megawatts of available capacity at transmission voltage but no process for taking in, reviewing and lining up data center requests so that capacity is not overcommitted. The third finding is that the code still lacks detailed standards for noise and vibration studies, water and wastewater studies and the closed-loop or free-air cooling systems it now requires.
The council already tightened the code on Oct. 13. Those changes, in effect since Oct. 27, require a specific use permit for any data center, push buildings and electrical equipment 300 feet from residential districts instead of 100, ban evaporative cooling and require utility demand studies and state grid approvals before a permit request reaches an agenda.