Seven Denton ISD campuses are scheduled for renovation work next summer, according to project registrations the district filed this month with the Texas Department of Licensing and Regulation. Together the filings put the estimated cost at about $28.7 million.
Every project lists the same window: work starting May 28, 2027, and finishing Aug. 31, 2027. Each one also includes secure vestibule upgrades at the school's entrance. Corgan Associates of Dallas is listed as the design firm on all seven.
The largest projects
E.P. Rayzor Elementary, 377 Rayzor Road in Argyle, carries the biggest estimate at $11,229,604. Beyond the entry work, the filing describes new interior finishes throughout the 77,726-square-foot school, a standardized classroom setup, new food service and playground equipment, and lighting and security upgrades.
Ann Windle School for Young Children, the district's preschool at 901 Audra Lane in Denton, is estimated at $5,908,710. Its scope adds interior finish work, food service equipment, resurfaced outdoor courtyards and replacement of lighting and the fire alarm system in the 37,097-square-foot building.
Navo Middle School, 1701 Navo Road, is estimated at $5,562,395 for interior finishes, an extended platform, and HVAC and lighting upgrades across 158,000 square feet.
Hawk Elementary, 2300 Oakmont Drive in Corinth, is estimated at $4,875,043. That project includes a roof replacement, a new freezer and cooler, and new lighting.
Smaller jobs
Three campuses have narrower scopes:
- Myers Middle School in Shady Shores: $539,336 for the entry work, an extended platform and a new fire alarm system.
- Rodriguez Middle School in Oak Point: $508,641 for the same three items.
- Shultz Elementary, 1502 Hanover Drive in Denton: $87,000 for the entry work and fire alarm replacement.