Downtown rail quiet zone, once due in 2019, is now set for 2027 construction in city bond report

A status report for Thursday's Bond Oversight Committee also shows Bonnie Brae estimates far above what voters approved and $15 million for affordable housing not yet issued.

Zane Boyd· AI-assisted, edited by Jake Team

November 2, 20263 min read

civic infrastructure - illustration, Jake Team LLC

Denton's railroad quiet zone for the downtown crossings, a project once scheduled to be finished by July 2019, is now expected to go out for bids late this year and start construction in the spring of 2027, according to a city status report on voter-approved bond projects.

The report goes to the city's Bond Oversight Committee at noon Thursday, Nov. 5, in the Council Work Session Room at City Hall, 215 E. McKinney St. Chief Financial Officer Matt Hamilton's staff prepared it to track spending and remaining costs on projects from the 2014, 2019 and 2023 bond elections.

The quiet zone

The project covers the Union Pacific crossings at McKinney, Hickory, Sycamore and Prairie streets, where added signals and other equipment would let trains pass without routinely sounding their horns. Staff attribute the years of delay to significant staffing changes at the railroad and to the city's own decision to add pedestrian crossing improvements to the scope.

Union Pacific has approved the plans, the report says, and the city is negotiating construction agreements. Staff are also applying for a federal Consolidated Rail Infrastructure and Safety Improvements grant to help pay for construction.

Bonnie Brae costs keep climbing

The report also tracks the long-running widening of Bonnie Brae Street. Voters in 2014 approved $9.5 million for the stretch north of Interstate 35E, phases 4A, 4B and 5; the revised estimate for those three phases is now $28 million.

Phase 4B, the widening from I-35E to the Scripture Street roundabout, is held until other phases are finished, with construction now expected to begin in the second quarter of 2027 and last about 18 months.

Phase 6, from University Drive to U.S. 77, was first budgeted at $6.1 million to reach Windsor Drive. Extended limits pushed its estimate to $31.1 million, with $11.06 million in federal money approved through the regional planning council. It is under construction and tentatively due in the second quarter of 2027.

Phase 3, south of the interstate, is expected to wrap up this month. TxDOT will build Phase 7 as part of its Loop 288 contract but has no schedule.

Waiting on money

Several 2023 projects are paced by when the city sells the bonds. Final design for the $15 million Water Works Park upgrade is complete and awaiting permits, but construction funding was shifted to the 2026-27 fiscal year. None of the $15 million voters approved for affordable housing has been issued; the current schedule spreads it from 2026-27 through 2030-31.

An inclusive playground budgeted at $3.45 million is still in design, with a 2027 opening targeted after a $750,000 state parks grant and staffing changes added time.

The city's issuance plan stretches the $291.4 million 2023 program into the 2032-33 fiscal year. A note on that schedule says it will be re-evaluated during the current fiscal year and may not stay extended.

Near the finish line

Fire Station 6, a $13.8 million replacement on a new site off Teasley Lane, is finishing its punch list and preparing for move-in, with completion expected by the end of this year.

Fire Station 5, rebuilt on its existing site for $15.8 million, is due in the spring of 2027, and the $20 million Linda McNatt Animal Care and Adoption Center, where foundations are going in, is projected for late 2027.

The committee advises the council and does not approve contracts. Its agenda also includes adopting a 2027 meeting schedule.

Sources

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

Share

Zane Boyd· AI-assisted, edited by Jake Team

Zane Boyd writes about community life, schools, public safety, and local events in Denton.

Related Stories

More in Texas