Ginnings Elementary rebuild would become a PK-8 academy under a $4.9 million change order up Tuesday

The change adds middle school dressing rooms, a second science lab and a fine arts room, pushes the total project cost to about $68.6 million and moves substantial completion to Oct. 26, 2027.

Zane Boyd· AI-assisted, edited by Jake Team

November 8, 20262 min read

Ginnings Elementary rebuild - illustration, Jake Team LLC

The campus Denton ISD is building to replace J.L. Ginnings Elementary would open as a prekindergarten-through-eighth-grade school under a construction change order on the trustees' consent agenda Tuesday night.

Balfour Beatty Construction, the district's construction manager at risk, submitted the $4,910,425 change order. Once design fees and other soft costs are added, it raises the project's total probable cost by $5,367,463, to $68,646,052. The construction contract itself would climb from $57,685,060 to $62,595,485.

What changes on the site

The signed change order form, prepared by the architecture firm Corgan, describes the project at 2525 Yellowstone Place as the Ginnings replacement "now PK-8 Academy." It says the elementary design is being revised for a PK-8 campus, with:

  • an activity room next to the gymnasium,
  • dressing rooms for middle school students,
  • a second science lab and a second art classroom,
  • a fine arts multipurpose room,
  • finishes and branding updated for a wider range of student ages.

The district's agenda summary describes the change more generally as revisions for an updated campus design and educational programming.

Cost and schedule

The work adds 155 days to the contract, and the form lists a new substantial completion date of Oct. 26, 2027. The architect signed it Oct. 23 and the contractor Oct. 30; it is not final until the district signs.

Of the roughly $457,000 in added soft costs, $319,178 is architect and design fees. Permit fees rise by $60,000 and materials testing by $40,000, according to the district's fee breakdown.

Voters approved tearing down and rebuilding Ginnings in the May 2023 bond election. Trustees approved the original $57.7 million guaranteed maximum price in August 2025, when the total project was budgeted at about $63.3 million.

Deputy Superintendent Jeremy Thompson and Chief Operations Officer Brandon Boyter are listed as the staff responsible, and the administration recommends approval. Consent items are approved in a single vote unless a trustee pulls one for discussion. Tuesday's regular meeting starts at 6 p.m.

Sources

meetings.boardbook.org

meetings.boardbook.org

meetings.boardbook.org

meetings.boardbook.org

Share

Zane Boyd· AI-assisted, edited by Jake Team

Zane Boyd writes about community life, schools, public safety, and local events in Denton.

Related Stories

More in Texas