Latest TxDOT status report lists $5.4 billion in Denton road work, with the next I-35 north segment ready to bid this month

The city's October mobility report puts the I-35 merge rebuild on track for January 2030, lists Loop 288 East and the Outer Loop as unfunded, and pegs an Outer Loop public hearing for January 2027.

Zane Boyd· AI-assisted, edited by Jake Team

November 7, 20262 min read

Denton Road Infrastructure - illustration, Jake Team LLC

State highway projects in and around Denton add up to about $5.37 billion in estimated construction costs, according to the October mobility report that city staff attached to the Nov. 6 Friday Staff Report to the City Council.

The report, prepared by the city's Innovative Transportation Solutions consultant, tracks 11 Texas Department of Transportation projects. Several are under construction, while some of the largest have no construction money yet.

Under construction

  • I-35/35E/35W merge: The $588.8 million rebuild of the interchange and the freeway from North Texas Boulevard to U.S. 77 is set to finish in January 2030. A TxDOT update dated Oct. 1 says drivers should expect nightly lane closures and one-lane frontage roads in several spots, and that the Loop 288 off-ramp was removed Oct. 3.
  • I-35E at Mayhill Road: The $123.5 million interchange rebuild began in January and is scheduled for completion in April 2029. The report notes the contract carries a 120-day delay. Brinker Road, closed since Aug. 24, was slated to reopen Oct. 17.
  • I-35 from FM 455 to View Road: Construction started in February on the $128.7 million widening, with completion projected for March 2029. A small traffic switch onto the new southbound frontage road between Lois Road and FM 455 is planned, date not yet set.

Next in line

On I-35 north of Denton, the segment from north of Rector Road to FM 455 is listed as ready to let for construction in November 2026. Two other segments, from U.S. 77 to Milam Road and from Milam Road to Rector Road, carry let dates of November 2028 and August 2027.

Two more, including the stretch to the Cooke County line, are marked as pending funding.

Waiting on money

  • Loop 288 East and U.S. 380 connector: Estimated at $1.262 billion, with $0 in construction funding. TxDOT and Denton County are working to see whether frontage roads can be built ahead of any main lane reconstruction, and a public hearing will follow approval of the schematic.
  • Outer Loop (I-35 to the Dallas North Tollway): The 23-mile freeway is estimated at about $1.55 billion, also with no construction funding. Schematic approval and environmental clearance are targeted for December 2026, and a public hearing is anticipated in January 2027.
  • FM 1515 and FM 1173: Widenings estimated at $69.5 million and $79.9 million are both listed as ready to let in December 2027, with FM 1515 pending funding.

Sources

lfpubweb.cityofdenton.com