Staff will hire a design consultant to study both city-owned sites, a report for Thursday's Bond Oversight Committee says. The same report puts Fire Station 6 near move-in and the animal shelter on track for late 2027.

Isabel Abbott· AI-assisted, edited by Jake Team

October 30, 20263 min read

Civic Planning - illustration, Jake Team LLC

Denton's voter-approved senior center and South Branch Library will go on two separate pieces of city land rather than share one campus, according to a report going to the city's Bond Oversight Committee on Thursday, Nov. 5.

The City Council gave staff that direction on Oct. 27, choosing the second of four options it had been weighing. The Active Adult Center, a $47.36 million project under Proposition F of the 2023 bond election, will be planned for 16.2 acres of city-owned land near Mack Park, off Audra Lane.

The South Branch Library, a $49.55 million project under Proposition G, will be planned for a 14.4-acre city-owned site on Ryan Road near Montecito Drive. The city bought the Ryan Road land in the fall of 2024.

The committee had recommended the separate-sites approach on Aug. 20. The other options were a shared site, expanding the existing library and senior center buildings, or moving into existing buildings elsewhere in the city.

A staff presentation for Thursday lists the trade-offs. Both new sites are city-owned, and the Ryan Road location offers room for outdoor space and the chance to sell or reuse the current South Branch building. The main drawback listed for both is higher long-term operating and maintenance cost. The Mack Park site's other listed challenge is its closeness to the American Legion Hall.

What comes next

Staff plan to hire a design consultant to study each site's feasibility and help gather public input, then bring the findings back to the committee and council during the 2027-28 budget process. Each project has $250,000 budgeted this fiscal year for site planning.

A funding timeline in the packet spreads the remaining construction money across fiscal years 2027-28 through 2031-32, though staff note that schedule will be re-evaluated this year.

The report also sets aside $969,000 for public art at the library. One concept under consideration would create outdoor art rooms inspired by the former "Chairy Orchard."

Other bond projects

The same report gives updates on work already under way:

  • Fire Station 6, being rebuilt on a new site off Teasley Lane, is finishing its punch list and preparing for move-in, with completion estimated in December. Its budget is listed at $13.8 million.
  • Fire Station 5 has its exterior masonry going up and is due in the second quarter of 2027, with a $15.8 million budget.
  • The Linda McNatt Animal Care & Adoption Center started construction in June and is installing foundations and utilities, with completion estimated in late 2027 on a $20 million budget.
  • Street reconstruction in Neighborhoods 2 and 6, paid for by the 2019 bond, rebuilt 118 street segments and 37 lane miles. The last two construction phases are due this month. The work has cost just over $85 million so far, including design and inspections, and staff project total savings of just under $2 million.

The Bond Oversight Committee meets at noon Thursday in the Council Work Session Room at City Hall, 215 E. McKinney St.

Sources

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

Share

Isabel Abbott· AI-assisted, edited by Jake Team

Isabel Abbott covers Denton city hall, the council, and county government.

Related Stories

More in Texas