Smart water meter pilot swaps 750 meters starting Oct. 26, ahead of a citywide changeover in December

A Water Utilities update for the Public Utilities Board on Monday lays out a $26 million Badger Meter program to replace every meter in the city by late 2029, plus a $628 million treatment plant expansion.

Zane Boyd

October 15, 20263 min read

Civic Water Infrastructure - illustration, Jake Team LLC

Crews are set to replace 750 Denton water meters with smart meters between Oct. 26 and Nov. 20, the pilot stage of a program that would eventually swap every meter in the city, according to a Water Utilities presentation prepared for the Public Utilities Board.

The board takes up the quarterly capital projects report in a work session after its regular meeting at 9 a.m. Monday, Oct. 19, in the Council Work Session Room at City Hall, 215 E. McKinney St. The item is a report and discussion, with no vote attached.

How the meter program works

The advanced metering infrastructure program would put a smart meter at every connection in the city, with endpoint devices that send readings over the cellular network. The old round meter boxes would give way to larger rectangular ones, and residents would get an online portal showing their usage in close to real time, the slides say.

Badger Meter is listed as the service provider at $26 million, with Black & Veatch as consultant at $614,535. A proof-of-concept round that replaced 50 meters ran Sept. 23 to Sept. 30. After the 750-meter pilot, staff plans to begin full deployment in mid-December and finish in the third quarter of 2029.

The usage portal, called Eye on Water, is slated to open to customers in early 2027.

The city applied July 30 for a state Water Supply and Infrastructure Grant and has answered two rounds of follow-up questions, the presentation says. It does not say how much the city requested.

Treatment plant work

The same report covers the Ray Roberts Water Treatment Plant, where an expansion would add 20 million gallons a day of capacity using low-pressure membrane units. Its estimated construction cost is $628 million. Construction is projected to start in the second quarter of 2027 and wrap up in the second quarter of 2032.

Freese and Nichols holds a $21.2 million design contract, and Archer Western Construction has a $2.8 million pre-construction contract. Membrane samples from pilot testing are to be examined at the end of October, with results going to the Texas Commission on Environmental Quality, and 60% plans are due in January.

A separate $40.8 million upgrade at that plant reached substantial completion June 8. TCEQ approved the plan for testing the plant's higher rated capacity in September, and staff expects that test to finish by year's end.

A project to replace chlorine gas and anhydrous ammonia at Ray Roberts with liquid chemicals is being redesigned after the only bid received in September 2024 was rejected as too high. It will be advertised again once the revised design is accepted; construction is estimated at $23 million.

Looking ahead, the five-year capital plan adds $205.4 million in new water projects, led by a $114.4 million transmission main from the Lake Ray Roberts plant and a $31.7 million elevated storage tank at Jim Christal. Counting work underway, in design and planned, the presentation puts the city's water infrastructure program at $974.6 million.

Sources

webapi.legistar.com

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com