Utility board weighs a $317 million second construction package for the new Pecan Creek wastewater plant

The Public Utilities Board on Monday considers the biggest piece yet of the city's rebuild of its only wastewater plant, bringing Sundt Construction's contract to about $409 million.

Zane Boyd· AI-assisted, edited by Jake Team

November 7, 20262 min read

Civic Infrastructure - illustration, Jake Team LLC

The largest construction package so far for Denton's new wastewater treatment plant goes before the city's Public Utilities Board at 9 a.m. Monday, Nov. 9, in the Council Work Session Room at City Hall, 215 E. McKinney St.

Staff are asking the board to recommend a second guaranteed maximum price amendment with Sundt Construction, the Irving-based construction manager on the Pecan Creek Water Reclamation Plant expansion. The amendment is capped at $317,024,218, made up of a $303,895,260 guaranteed price and $13,128,958 in contingency that only the city can draw on, with written sign-off from its project manager.

It would bring the total value of Sundt's construction contract to $409,345,783. The board's vote is a recommendation; the City Council has the final say.

Why the city is building new

Pecan Creek, built in 1963, is the only wastewater plant the city has. It is permitted for 21 million gallons a day and now averages about 15 million, or 71% of its limit, according to the agenda sheet.

Texas Commission on Environmental Quality rules require a utility to begin designing added capacity once flows hit 75% of the permit and to begin construction at 90%, and the city began design work in 2023. TCEQ approved a new 30-million-gallon-a-day discharge permit in 2025.

A condition assessment of the 60-year-old plant in August 2025 concluded that replacing it would cost less than repairing and enlarging it. A comparison in the staff presentation puts the rehab-and-expand route at about $636.7 million, finished in July 2034, against about $503.8 million for a new 30-million-gallon plant finished in December 2031, a difference of roughly $133 million.

The new plant will use membrane bioreactor treatment, along with new headworks, solids screening, solids handling, UV disinfection and an operations building.

What this package covers

Work began April 6 under the first package, which the council approved March 3 for about $92.3 million and which covered earthwork, site utilities, surveying and testing. The second package spans 11 scopes, including concrete, precast concrete, structural steel, metal buildings, electrical work, bridge cranes and the early purchase of treatment equipment.

A third and final package is out for bids and is expected before the council sometime in 2027.

The agenda sheet lists three funding sources for this round: about $101.7 million in city capital bonds, about $155.4 million through the federal WIFIA loan program and $60 million from the Texas Water Development Board. Spending is projected to peak at about $119.5 million in the 2027-28 fiscal year, and the city expects the plant to be finished in late 2031.

Residents can comment on agenda items through the city's eComment system until the meeting starts.

Sources

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

Share

Zane Boyd· AI-assisted, edited by Jake Team

Zane Boyd writes about community life, schools, public safety, and local events in Denton.

Related Stories

More in Texas