Council weighs staff's case for a data center moratorium Tuesday, citing about 75 megawatts of spare power

Staff findings point to limited Denton Municipal Electric capacity and water demand as reasons to pause new data centers, while a separate vote that night would require 300-foot setbacks and closed-loop cooling.

Isabel Abbott

October 12, 20263 min read

Denton City Council members will spend part of Tuesday afternoon deciding whether the city has made its case for a temporary halt on new data centers.

A 2 p.m. work session on Oct. 13 is set aside for the written findings a moratorium ordinance would need under state law. Development Services staff are asking the council to endorse those findings, change them or stop the process.

If the council moves ahead, the second required public hearing and a first reading are scheduled for Oct. 27, with a final vote on Dec. 1.

What staff are pointing to

The staff report lists three legal grounds. On water, the city can produce up to 48 million gallons a day and treat 21 million gallons of wastewater, and peak days have reached 42.2 million and 25.7 million gallons. Staff say data centers that rely on evaporative cooling could exceed what those systems can handle.

On electricity, the report says Denton Municipal Electric has roughly 75 megawatts available for new connections and no process for taking in, studying and batching data center requests. A state directive is limiting new interconnections above 75 megawatts, but the city still handles requests below that size.

The utility has proposed $300 million in transmission projects to the state grid operator, ERCOT, that would not be finished before 2031 at the earliest, according to the report.

The third ground is time to write detailed technical standards, which staff say the code currently lacks.

A moratorium cannot block applications already on file, could cover the city and its extraterritorial jurisdiction, and would need votes from three-fourths of the council. It could last 90 days, with one 90-day extension, and could not be reimposed on the same area for two years. A staff timeline shows it ending May 31.

The two existing projects

Denton already has two large data centers on city land: Core Scientific, which leases about 78 acres with a power agreement for up to 391 megawatts and uses closed-loop cooling, and WAHA/Qumulus AI, which leases 4 acres with up to 20 megawatts and air cooling.

Staff say both pay all of their power and transmission costs, and together they have generated more than $3.1 million in property taxes, $475,000 in sales tax and $8.8 million in electric return and franchise fees.

New code rules up for a vote that evening

Separately, a 6:30 p.m. public hearing covers code changes the Planning and Zoning Commission backed 5-0 on Sept. 23. They would require a specific use permit for warehouse data centers in light industrial, heavy industrial and public facilities zones and bar them from office and corridor districts.

Setbacks from homes would grow from 100 feet to 300 feet, cooling would have to be closed-loop or free-air, water and wastewater studies would be required up front, light spill at a residential property line would have to be zero, and state utility and ERCOT approvals would be needed before a permit request reaches an agenda.

Staff say these rules apply only inside city limits and only to new development.

Sources

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

KERA News

ntdaily.com

Share

Isabel Abbott

Isabel Abbott covers Denton city hall, the council, and county government.

Related Stories

More in Texas