Utility board takes up the $317 million second phase of the city's new wastewater plant on Monday

The package would push Sundt Construction's contract for the Pecan Creek Water Reclamation Plant past $409 million. A new 30-million-gallon plant is due in late 2031, replacing a facility first built in 1963.

Zane Boyd· AI-assisted, edited by Jake Team

November 3, 20262 min read

Civic Infrastructure - illustration, Jake Team LLC

Denton's Public Utilities Board is set to consider a $317 million amendment on Monday, Nov. 9, for the next stage of work at the Pecan Creek Water Reclamation Plant, the only wastewater treatment plant the city has.

The item, posted Tuesday for the board's 9 a.m. meeting at City Hall, is the second of three guaranteed maximum price packages under the city's construction manager at risk contract with Sundt Construction. If the board recommends it and the City Council later approves it, the total contract would reach $409,345,783.

What the money buys

According to the staff agenda sheet, the second package covers 11 scopes of work, including concrete and precast concrete, structural steel, metal buildings, electrical work, site utilities, bridge cranes and the early purchase of process equipment. Of the $317,024,218 requested, $303,895,260 is the guaranteed price and $13,128,958 is a contingency that only the city's project manager can release in writing.

Staff list three funding sources: $101.7 million in capital bonds, $155.4 million in federal WIFIA loan money and $60 million from the Texas Water Development Board. Spending is projected to peak at about $119.5 million in the 2027-28 budget year.

A third and final package, still out for bids, is expected to reach the council in 2027.

Why the city is building new

The plant opened in 1963 and has been expanded several times to its current 21 million gallons a day. Average flows now run about 15 million gallons, or 71% of its permitted limit, the city says. State rules require utilities to start designing more capacity at 75% and to begin building at 90%.

A 2025 condition assessment concluded that replacing the plant would cost less than rehabilitating and expanding the 60-year-old structures. A city presentation estimates the rebuild-and-expand route at $636.7 million with completion in July 2034, compared with $503.8 million for a new 30-million-gallon plant finished in December 2031, a difference of about $133 million. State regulators approved a 30-million-gallon discharge permit in 2025.

The new facility will use membrane bioreactor treatment, which the city says produces cleaner effluent and less sludge, along with new headworks, ultraviolet disinfection and solids handling.

Work already underway

The council approved the first $92.3 million package in March, and construction started April 6 on earthwork, underground utilities and other early site work. Sundt announced the groundbreaking in a trade publication this week, saying the existing plant will stay in operation throughout construction.

"This work strengthens the backbone of Denton's wastewater system," said Matt Bothun, Sundt's Texas regional manager for water and wastewater.

The city projects completion in the fourth quarter of 2031.

Sources

legistar2.granicus.com

legistar2.granicus.com

legistar2.granicus.com

acppubs.com

Share

Zane Boyd· AI-assisted, edited by Jake Team

Zane Boyd writes about community life, schools, public safety, and local events in Denton.

Related Stories

More in Texas